PHASE – I
Received Part Drawing / Standard from Customer end. After received
part drawing & standard review of customer inputs & material
specification.
Product Manufacturing review meeting
If required, cost negotiation and spec. meeting (if necessary) shall
be done with the customer for the same and Receive LOI / Purchase Order to
Customer and go ahead for development department.
Product manufacturing timing planning review meeting (APQP Plan)
Prepare Bill of material
If Initial Feasibility & Risk Analysis Feasible prepares
Quotation, discuss and take approval from top management and send to customer
Prepare Development Time line Plan with clearly defined
responsibility of CFT Team and target date.
(Also prepare the micro plan for each activity item of time line plan
with defined activity review frequency) and also prepare the responsibility
matrix.
At the time of Development time line preparation, it shall be ensured
that all the past problem related to similar product has been taken care.
If LOI & Purchase Order is Feasible, Review of Phase – I
Activities.
Phase – I Activities feedback
give to Plant Head and review required within two weeks.
|
Part drawing / standard / Samples
Part Drawing / Standard
LOI & Purchase Order
APQP time plan
BOM
List of Critical Characteristic& Drawings, CSR
MOM & PFD
Project Review record
LOI & Purchase Order
|
Review of Customer Input
List of Critical Characteristic.
Go to Dev. Dept.
Time management
Go to dev. Dept.
Feasibility & Risk Analysis
Go to all dept.
Past Problem review record
Review of Phase – I Activity (MOM)
|
Head Engg.
Head Engg.
Head Engg.
Head Engg.
Head Engg.
Head Engg.
Head Engg.
|
10
11
12
13
14
|
PHASE – II&
PHASE – III (Product & Process Design and Development.
Prepare Development Time line Plan with clearly defined
responsibility of CFT Team and target date
and also prepare the responsibility matrix.
Responsibility Matrix shall explain the Cross Function team as below.
CFT Members:-Mkt, Engg., Dev,
QA, Production, Store, Purchase, Dispatch, Tool room.
Development plan Activity
Review Frequency shall be once in a week by
CFT and once in month by top
management or customer specific.
Responsibility Matrix shall contain the below (Micro plan activity)
activities during preparation of time line plan.
a)
TOOL & FIXTURE PREPARATION
b)
EQUIPMENT / MACHINE PREPARATION
c)
GAUGE \ INSP EQPT. PREPARATION
d)
ADVANCE DESIGN CHANGE INFORMATION
e)
PAST TROUBLE, RE-OCCUR PREVENTION
VERIFICATION
f)
SPEC TEST VERIFICATION PLAN
g)
CTQ PARAMETERS IDENTIFICATON
h)
MAKING PROCESS FLOW CHART
i)
PROCESS FMEA VERIFICATION PLAN
j)
MAKING PRE-LAUNCH CONTROL PLAN
k)
TIER 3 READYNESS
l)
LOCAL/IMPORTED RAW MATERIAL PLAN
m)
PACKAGING TRIAL PLAN
n)
CAPACITY VERIFICATION PLAN
o)
FLOOR PLAN LAYOUT
p)
CHARACTERISTICS MATRIX
q)
PRELIMINAY PROCESS CAPABILITY STUDY PLAN
r)
MEASUREMENT SYSTEM ANALYSIS PALN
Prepare Listing of Jig, Fixtures, Gauges, Equipment, and Machines
Tools.
Prepare B.O.P & Part Drawing (If Required), and get Approval if
required.
Prepare Operator training plan
Prepare sample submission to customer timing plan for 4 phases: PP
trial, MPT, Pilot trial and SOP
|
Feasibility Study, Risk Analysis, Contract Review & LOI &
Tool Go, Purchase Order, CSR
Prelaunch Control Plan, FMEA, OPS, Inspection Standard
Development Plan
Approved Customer input
BOM, Drawings
Training plan
Submission report
|
Development Plan
Responsibility Matrix with CFT Team, Micro plan,
Project Review record.
Production Control plan, Capacity confirmation, SPC, MSA, Spec Test
Results, Layout inspection
List of Jig, Fixture, Gauge, Equipment,
Machines & Tools
BOM, Drawings
Trained
operators
|
Dev Head
Head Dev
Head Dev.
Head Dev.
Head Dev.
|
12
13
14
15
16
17
18
|
PHASE – IV (Product and process
Validation)
Conduct
Significant Product run (Parts / 8 Hrs) or Customer specific (Capacity
Confirmation)
Conduct Cpk &
MSA Study and Process Qualification (If Required)
Conduct internal
& External packaging evaluation
Prepare the
production control plan
Confirm the
PFMEA implementation results
Confirm the Spec
Test Results
Conduct Layout
inspection for 05 Samples or Customer Specific.
PSW Submission
to Customer with PPAP Level III or Customer Specific requirement.
If Completion Ok, then release Control
Plan, S.O.P, FMEA for Production process.
If Completion is not ok, then re-Start
Ram pup Activities (Review of targets & Monitoring of Process Stability)
After PSW Sign
off with the customer, Start
Ramp up
Activities (Review of targets & Monitoring of Process Stability)
And Conduct the
review of quality management system.
Production part
approval by customer
Prepare
production control plan, refer the procedure of control plan QSP:33
Prepare Quality
Planning sign-off and Management support
|
Production Control plan, Capacity confirmation, SPC, MSA, Spec Test
Results, Layout inspection
Level III PPAP or as per customer requirement
All targets
All targets
Level III PPAP or as per customer requirement, Status of initial
supply record
Inspection report
Control plan
Quality inspection report
|
Level III PPAP or as per customer requirement
Signed PSW
Monitoring
Monitoring
APQP Check list
APQP Sign off
SOP
Quality review
Quality Management System Review check sheet
|
Production& NPD
NPD
NPD
NPD
QA & QMS
Head Dev, QA & Production
Head Engg.
|
20
21
22
22
23
24
|
PHASE - V
Get feedback from customer / communicate
to customer for further action.
Initial control period initiation.
Monitor production, defect and dispatch
Review learning of Project &
Review of Phase – V Activities.
Phase – V Activities feedback give to Plant Head and review
required within two weeks.
APQP project file has been completed as
per the checklist & signoff
APQP file document has been reviewed once
in a year or when any customer complaint / major process issue has been
noticed.
|
Feedback report
Control plan, SPC Plan & SOP
Monitoring
All targets
Completion Results
APQP file
Quality issue
|
Action Plan
Control Plan & S.O.P Production
Smooth part production
Monitoring
Future reference
Smooth part production
|
NPD
NPD
CFT with Plant Head.
Head Engg.
HeadEngg.
CFT with Plant Head.
|
5. Reference Procedure:-
5.1 Initial Supply Control, 5.2 Change Management, 5.3 Control of
Documents, 5.4 Control of Records, 5.5 Control of NCR, 5.6 Supplier Quality Assurance,5.7
Tooling management, 5.8 Production Part Approval process, 5.9 failure mode
& effects analysis, 5.10 Identification &traceability, 5.11 4 M
change control, 5.12 corrective & preventive action
6.1 PPAP COVER PAGE F/ENGG/01
|
6.2 APQP/Part Development Timing plan F-DEV-01
|
6.3 Customer Drawing Review Sheet F-DEV-02
|
6.4 IPC Sign Off F-DEV-03
|
6.5 Team Feasibility F-DEV-04
|
6.6 Process Flow Diagram F-Dev-05
|
6.7 PFMEA F-DEV-06
|
6.8 Control Plan F-DEV-07
|
6.9 List of Tooling F-DEV-08
|
7.0 Product Quality Sign off F-DEV-09
|
7.1 Part Submission Warrant F-DEV-10
7.2 Cross Functional Team F-DEV-11
|
7.3 Raw Material Test Planning F-DEV-12
|
7.4 Packaging Standard F-DEV-13a
|
7.5 Things Going Right Things Gone Wrong F-DEV-13
|
7.6 List of Development Items F-DEV-14
|
7.7 FMEA Review Plan F-DEV-15
|
7.8 Contract Review Check Sheet F-DEV-16
|
7.9 Part Development History Sheet
F-DEV-17
|
8.0 APQP Meeting F-DEV-18
|
8.1 Checking Aids F-DEV-19
|
8.2 Engineering Change Request F-DEV-20
|
8.3 Risk Analysis F-DEV-21
|
8.4 Operator Contingency Plan F-DEV-22
|
8.5 ECN Tracking Sheet F-DEV-23
|
8.6 APQP Matrix F-DEV-24
|
8.7 Tool Development Plan F-DEV-25
8.8 List OF DEFECTS Unable TO Capture
F-DEV-26
8.9 Bill of Material F-DEV-27
|
9.0 PPK/CP PLAN & REPORT F-DEV-28
9.1 List of Poka Yoke
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7.0 ISO/TS
16949 Clause Reference Number : 7.2.1,
7.2.2, 7.2.3, 7.3.2.2, 7.3.2.3, 7.3.3.
|